BrightSource Energy submitted a $10 million bid for the 500 MW concentrated solar power plant as part of the court-approved auction of four solar energy projects Solar Trust had in development. |
||
|
|
||
|
|
||
|
Solar thermal developer BrightSource Energy has already filed a $10 million bid for the smaller of the two projects, the 500-megawatt Palen project 10 miles east of Desert Center. |
||
|
|
||
|
|
||
|
BrightSource Energy is seeking to buy an unbuilt 500- megawatt concentrating solar thermal power plant from the bankrupt Solar Trust of America, according to Bloomberg. |
||
|
|
||
|
|
||
|
Yesterday, Solar Millennium AG, the majority owner of the equity of Solar Trust of America, announced the initiation of insolvency proceedings in Germany. |
||
|
|
||
|
|
||
|
The third Solar Millennium AG corporate bond amounting to € 20 million, which was issued on 22 August 2006, was repaid in full to investors yesterday. |
||
|
|
||
|
|
||
|
Corporate strategy adjusted to changed market requirements particularly in the U.S. to secure sales and earnings. |
||
|
|
||
|
|
||
|
Leading U.S. Solar Developer Honored at CSP Today’s 2011 Conference in Las Vegas. |
||
|
|
||
|
|
||
|
Solar Trust of America, the integrated solar industrial solutions company currently developing the 1,000 MW Blythe Solar Power Project among other projects, announced a new corporate naming convention and structure. |
||
|
|
||
|
|
||
|
With a capacity of 1,000 megawatts (MW), Blythe will be the largest solar power facility in the world and will be providing energy on s scale comparable to commercial nuclear and fossil-fueled power plants. |
||
|
|
||
|
|
||
|
Back in April, I had the pleasure of announcing that the Department of Energy had extended our largest conditional loan guarantee for a solar project – $2.1 billion to support a concentrating solar thermal power plant ne |
||
|
|
||
|
|||
|
The electricity generated in Blythe 1 and 2 will be purchased by the US utility Southern California Edison (SCE). |
||
|
|
||
|
|||
|
On Friday 17 June 2011, U.S. Secretary of the Interior Ken Salazar and California’s Governor Jerry Brown will break ground on the solar-thermal power plant in Blythe, the world's largest facility of its kind. |
||
|
|
||
|
|
||
|
Department of Interior Secretary Ken Salazar Joins as Guest of Honor. |
||
|
|
||
|
|
||
|
Solar-thermal power plants remain the essence of the brand and the focus of activities |
||
|
|
||
|
|
||
|
The new company will develop stand-alone PV sites, as well as projects with CSP and PV in the same location. |
||
|
|
||
|
|
||
|
Solar Trust of America (STA) is a joint venture of the Solar Millennium Group (70%) and the Ferrostaal Inc. (30%) and covers important business fields in the value chain for solar thermal power plants in the region of No |
||
|
|
||
|
|
||
|
Solar Trust America is a joint venture between German firms Solar Millennium and Ferrostaal. The group already started preliminary construction of the project last fall. |
||
|
|
||
|
|
||
|
For the first time in mankind’s history, a solar power facility will be built at a scale and output capacity comparable to large coal fired and nuclear power plants. |
||
|
|
||
|
|||
|
I have good news. Today, the Department of Energy offered a $2.1 billion conditional commitment loan guarantee to support a concentrating solar thermal power plant near Blythe, California. |
||
|
|
||
|
|
||
|
With the conditional commitment, the most important prerequisite for the successful financial close for the first two power plants at the Blythe location is in place. |
||
|
|
||
|
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |